|
Issue |
Finding |
Result |
|
A crane rental agreement called for
the rental of various cranes at hourly rates, inclusive of an
operator. The cranes were not to be billed while idle.
|
Review of equipment billings and
operator timecards indicated that cranes were billed for a
weekly minimum, irrespective of hourly use and that the crane
hours exceeded operator hours.
|
The client asked for, and received,
credit for a portion of the excess billing
$101,000
Recovery
CRW Archives, 1998 |
|
Analytical review of small tools
purchases indicated that tools expense was growing while capital
spending was declining. |
Auditors recommended inventory,
utilization, and other internal controls adopted by management. |
Annual costs of small tools fell by
more than $1 MM.
$1 Million Savings
Source:
Internal Auditor, 8/95, p.78
(contributed by San Diego Chapter of IIA) |
|
A contractor called upon to perform
emergency repairs after a fire converted the contract with the
owner to a fixed price of $19 million. |
The internal auditor reviewed the
supporting documentation used to arrive at the fixed price and
found inflated costs, including equipment charged out at 2000
miles when the actual round trip was only 100 miles
|
All payments to the contractor were
suspended until the agreement was restructured.
Source: Internal Auditor,
4/99, p.75 (contributed by Mount Diablo Chapter of IIA) |
|
While a maintenance contract contained
hourly, weekly, and monthly amounts, it also required for the
lowest rate to be applied to the rental period. |
The auditor noted that in every
instance the highest rate, the hourly rate, had been charged
although lower weekly or monthly rates applied to the
transactions.
|
The company was able to secure
recovery from the contractor.
Source: Internal Auditor,10/96,
p. 73 (contributed by the Tucson Chapter of IIA) |
|
The equipment rental agreement called
for the company to make routine repairs and maintenance. Major
repairs were the lessor's responsibility. |
The internal auditor found that the
lessor had billed the company for engine rebuilds. |
The company recovered $4 thousand.
$4,000
Savings
Source: Internal Auditor,p.64
(contributed by Dallas Chapter of IIA) |
|
The contractor separately purchased
and billed small tools covered by another contract. |
The auditor reviewed the various
contracts with the contractor and discovered the duplicated
costs. |
The owner recovered the duplicated
tools cost that had been billed from the contractor.
$6,375
Recovery
Source: AMG
archives |
|
The basis for small tool and field
consumable billings was overstated. |
The auditor reviewed the contract
provisions and determined that certain labor costs should have
been eliminated from the rental base. |
The contractor refunded the excess
amount collected from the owner.
$45,880 Savings
Source: AMG
archives |
|
Equipment was rented from a major
subcontractor who was performing a cost-plus subcontract. The
rates charged were from the subcontractor's "standard' Hourly
rate schedule. |
The auditor performed a review of
equipment rentals for the project. It was discovered that the
rental rates charged by the subcontractor substantially exceeded
those available from third party rental companies, allowing full
cost recovery ion approximately 6 weeks.
|
The auditor recommended that the
subcontractor be paid at market rates for equipment rental.
$15,425
Recovery
$45,000+ Savings
Source: AMG
archives |
|
The company purchased construction
equipment to save rental costs, moving the equipment between
project sites. In some instances the company would purchase
equipment from contractors. |
The auditor secured an equipment
inventory and sought to account for all equipment purchases. |
The results of the review were the
discovery of duplicate purchase orders for the same equipment
and incidences of missing equipment.
$7,650
Recovery
$35,000 Lost
Equipment
Source: AMG
archives |